Maybe you are thinking about putting up a bucket elevator and want to get some rough estimates on costs? Maybe you've gotten bids from several contractors to put up a bucket elevator, but the bids came back with different elevator heights? What should it cost to put up a bucket elevator? To answer these questions, first you need to know the answer to the question, "how tall should my bucket elevator be?"
The height of your bucket elevator is determined by three factors: Required spout angle. How far away do you need to spout? How tall is your highest discharge point?
You'll find that there are a lot of opinions about what is correct, and what you might "get away with" when it comes to spout angle. The safe rule of thumb is, dry grain typically flows reliably in a spout at an angle of 45° or more. High moisture grain, sunflowers and ground feed generally require spouts at a minimum angle of 60°.
You might hear some say, "you don't need to be at 45° with your leg spouts. You can get by with 43° or even 40°. Working within these shallower spout angles is a way for some to shorten the height of the leg they are bidding. Buyer beware! While you might save a couple bucks putting up the elevator leg that is the shortest, it is generally not the place to try and save money. Remember, if the bucket elevator you install is too short, it is very difficult (read:expensive) to fix later. If your material can't efficiently flow down your spouts at the rated capacity of the rest of the upstream system, you'll have to slow all the equipment down upstream. This obviously reduces your throughput and increases your unload time. In a particularly bad scenario, overfeeding a spout at too shallow of an angle can cause plugging of the bucket elevator. This is something people strive to only do once!
I think you get my point. Here is one of the easiest ways I know to calculate how tall your bucket elevator should be.
In the illustration below, assume the grain tank shown is the furthest point away from where you'd like to place your bucket elevator. For a 45° spout angle, dimension A and B must equal one another. For a 60° spout angle, dimension B should equal dimension A x 1.75. All other discharge points (closer to the leg) can generally be assumed to be at spout angles steeper than your shallowest spout angle.